Around the Railways in Worcestershire, Dave Pagett's Blog
Welcome to Dave Pagett's new blog on the subject of Railways in Worcestershire. Any newsworthy events will be displayed here in association with the "Fotopic" website.
Saturday, 15 January 2011
S.V.R. Engineering work at Bewdley
Work has begun in earnest at various locations along the route of the S.V.R. with contractors now on-site at a number of locations. Some fairly substantial projects have now commenced in order to make good forty years of intensive operation which had taken it's toll on the railway's infrastructure, especially the track itself and some of the fixed structures. At the same time as this work is on-going, the S.V.R. is taking the opportunity of the enforced curtailment of train services to undertake a number of less substantial jobs while the weather, at present, is reasonably favourable. The cattle dock spur on the down side of Bewdley yard is one such task, which consists of replacing the track and it's formation with new materials, mainly in the form of concrete sleepers. To facilitate these measures, all the rolling stock which normally occupies this line has had to be temporarily relocated onto platform one whilst the work takes place. Doris & Sue in the Station Fund coach and Trish & Graham Stevens who man the Erlestoke Manor sales fund coach are enjoying(?) a change of scenery for the time being, but I am assured that, in the meantime, both are still very much open for business.Now that there are no service trains to deal with at the moment, and in lieu of normal duties, Bewdley station staff are also busy on jobs in and around the station site, especially the items on the gardening agenda.
Friday, 7 January 2011
4th January 2011 - H.S.T. in trouble
4th January 2010, Bromsgrove
1V54 the 0632 Dundee-Plymouth (power cars 43303 +43384) failed at approx.14.00 at Dunhampstead, between Stoke Works and Abbotswood Junctions with total loss of air and unable to move forward.The plan to rescue the train was to provide assistance with Freightliner locomotive no: 66555 which was following with a coal train. 66555 dumped its wagons in Stoke Wks Jct loop and was attached to 43303 and propelled the HST to Bromsgrove station to detrain the passengers; this happened at around
19:00, some 5hrs after the train had failed. The HST was then to be pushed back up the Lickey incline with 66555 as a banker.
However halfway up the climb 66555 itself failed. The train was then brought back down the bank and left in the sidings at Bromsgrove.
The following day Colas hired in 57308 and hauled the HST back up the Lickey incline as (5D02) to Barton under Needwood.
The photo shows 57308 hauling 43384 / 303 out of the sidings at Bromsgrove.
Report by Steve Widdowson.
Sunday, 2 January 2011
S.V.R. engineering works and associated train movements
At the begining of 2011 the Severn Valley Railway began preperations in connection with a number of major civil engineering projects on the line, the most important of which are: 1) Drainage and track replacement work at Arley station, and between Arley and Victoria bridge. 2) Waterproofing of Bewdley south (Sandbourne) viaduct and associated trackwork, and 3) Relaying of the down yard headshunt at Bewdley.
These works will require a considerable amount of temporary displacement of static rolling stock to other locations, including the removal of a number of items from Arley, together with the Erlestoke Manor Fund coach and the Station Fund coach at Bewdley which will reside in platform one, as there are no booked public train services for the time being over the winter period. Meanwhile the class 20 diesel locomotive no: D. 8188 will be keeping itself occupied on these duties.
These works will require a considerable amount of temporary displacement of static rolling stock to other locations, including the removal of a number of items from Arley, together with the Erlestoke Manor Fund coach and the Station Fund coach at Bewdley which will reside in platform one, as there are no booked public train services for the time being over the winter period. Meanwhile the class 20 diesel locomotive no: D. 8188 will be keeping itself occupied on these duties.
Monday, 27 December 2010
Stabling of H.S.T.'s in Hereford sidings for F.G.W.
During the Christmas 2010/New Year 2011 period, F.G.W. have been making use of the "Hereford Sidings" in Worcester yard in order to provide overnight berthing accommodation for a number of H.S.T. sets the company operates on it's principle long-distance services. The main reason for this policy is in order to overcome difficulties caused by the major infrastructure work connected with the re-modelling of Reading station which is being undertaken on behalf of Network Rail during this period.
The Hereford sidings consists of two groups of lines on the south side of the yard, the shorter group of four having buffer stops. The longer group consists of three sidings usually accessed from the "through goods" lines and are normally used to temporarily recess traffic, but may also be accessed to/from the main lines directly via a facility known as the "North Sidings Ground Frame", a small signal box that operates in conjunction with the main 'box at Shrub Hill. It is only manned when required for use.
This latter facility has seen very little use in recent years and although maintained in working order, it had to be overhauled in order to make it fit for purpose, together with it's associated trackwork. This work was undertaken by F.G.W.'s contractor Ganymede Ltd., who have also installed a "shore supply" power facility, together with local Network Rail signal engineers.
At present, sidings nos. 1 and 3 have returned to use, with number 2 siding awaiting refurbishment in anticipation of a more permanent arrangement coming into force at the start of the May 2011 timetable. F.G.W.'s operations will then become constrained due to the commencement of works in the London area in connection with the Crossrail project, the main consideration for the implementing these arrangements at Worcester.
An initial test train was run on Thursday 23rd December in order to confirm that all was well and the facilities were officially brought into use later the same day. The first "in service" working to become stabled (on number.3 siding) was on Christmas eve with the empty stock which had worked into Worcester as the 17.50 from London Paddington. It was reported that some difficulties arose with the stabled sets over the Christmas weekend period, caused by diesel fuel freezing in the sub-zero temperatures.
The Hereford sidings consists of two groups of lines on the south side of the yard, the shorter group of four having buffer stops. The longer group consists of three sidings usually accessed from the "through goods" lines and are normally used to temporarily recess traffic, but may also be accessed to/from the main lines directly via a facility known as the "North Sidings Ground Frame", a small signal box that operates in conjunction with the main 'box at Shrub Hill. It is only manned when required for use.
This latter facility has seen very little use in recent years and although maintained in working order, it had to be overhauled in order to make it fit for purpose, together with it's associated trackwork. This work was undertaken by F.G.W.'s contractor Ganymede Ltd., who have also installed a "shore supply" power facility, together with local Network Rail signal engineers.
At present, sidings nos. 1 and 3 have returned to use, with number 2 siding awaiting refurbishment in anticipation of a more permanent arrangement coming into force at the start of the May 2011 timetable. F.G.W.'s operations will then become constrained due to the commencement of works in the London area in connection with the Crossrail project, the main consideration for the implementing these arrangements at Worcester.
An initial test train was run on Thursday 23rd December in order to confirm that all was well and the facilities were officially brought into use later the same day. The first "in service" working to become stabled (on number.3 siding) was on Christmas eve with the empty stock which had worked into Worcester as the 17.50 from London Paddington. It was reported that some difficulties arose with the stabled sets over the Christmas weekend period, caused by diesel fuel freezing in the sub-zero temperatures.
Monday, 6 December 2010
Saturday 4th December - S.V.R. "Santa Specials"
Saturday 4th December saw the beginning of the seasonal "Santa Special" services, running from Kidderminster Town to Arley for Santa's grotto, on the Severn Valley Railway. These trains are run at a frequency of every half-an-hour throughout the day at weekends up until and including Christmas Eve.
Thursday 2nd December 2010 - Single Line Working
For almost a week an emergency speed restriction had been in force over both the up and down lines between Worcester Shrub Hill and Norton Junction as a result of outstanding track defects becoming overdue for rectification. Rob Matthews engineering possession the previous Saturday night had been extended to cover these lines so that the work could take place, but a lack of resources (and the weather conditions) meant that the work could not be completed. Ron Davies's midweek blockages also made an attempt to finish the job off but was also thwarted by the same difficulties. Early on the Thursday morning it became clear that there would be an over-run with the original hand-back time deadline being missed by at least a couple of hours.
Luckily Ron was able to hand back the down line at about 5 o'clock and so a start was made in arranging "single-line-working" between Shrub Hill and Norton Jcn. The local Ashchurch mobile operations manager Paul Gardner acted as Pilotman with the 05.02 to Paddington travelling wrong line at about 05.20. Next train in the right direction was 6M11 the Margam to Round Oak steel which was routed into the yard. A considerable amount of disruption also occurred with the platforming of London Midland services. At about five-to-six my colleague Steve Lewis came to relieve me of duty and so I left the situation in his capable hands and returned home for a well-earned break. (I was absolutely gutted at having to leave !) When I returned to work the following week, I discovered that S.L.W. had continued until 09.20, with the up line not handed back until turned 10 o'clock.
Luckily Ron was able to hand back the down line at about 5 o'clock and so a start was made in arranging "single-line-working" between Shrub Hill and Norton Jcn. The local Ashchurch mobile operations manager Paul Gardner acted as Pilotman with the 05.02 to Paddington travelling wrong line at about 05.20. Next train in the right direction was 6M11 the Margam to Round Oak steel which was routed into the yard. A considerable amount of disruption also occurred with the platforming of London Midland services. At about five-to-six my colleague Steve Lewis came to relieve me of duty and so I left the situation in his capable hands and returned home for a well-earned break. (I was absolutely gutted at having to leave !) When I returned to work the following week, I discovered that S.L.W. had continued until 09.20, with the up line not handed back until turned 10 o'clock.
Wednesday 1st December 2010 - Compass Tour to Edinburgh.
Wednesday 1st December 2010 saw the running of an excursion organised by CompassTours from Worcester Shrub Hill to Edinburgh. With the weather as it was, especially worse the further north you went, this looked like a decidedly risky undertaking but, as it turned out, all went very well indeed.
The empty stock arrived from Crewe at about 03.00 in the morning and had to be routed onto the up through goods line, as the thirteen coach train, top-and-tailed by class 67 locomotives, required the leading engine to run-round in order to double-head the excursion away. These movements were an impossibility to undertake in the station itself with such a lengthy consist. Part of these manoeuvres meant propelling the train out of the yard and onto the down main line so it could draw forward into platform one. Departure was on-time at 05.00 which necessitated the re-platforming of the 05.02 F.G.W. service to Paddington onto platform two.
Although the excursion was heavily delayed en-route, arrival time at Edinburgh was only fifteen minutes late, and a more-or-less right time departure on return saw an arrival back at Worcester nearly twenty minutes EARLY. This caused a few problems at Shrub Hill as the excursion arrived before the late-running last train from Snow Hill. Luckily the train was top-and-tailed on arrival and after some deliberation it was decided to return the coaching stock to Crewe in this formation. The train ground to a halt on the Lickey incline and had to be assisted by a following freight service but eventually made it into Birmingham some time later.
Steve Widdowson's photograph shows a snow-encrusted 67030 being prepared to leave Worcester at one'o clock on the 2nd with the empty stock bound for Crewe.
The empty stock arrived from Crewe at about 03.00 in the morning and had to be routed onto the up through goods line, as the thirteen coach train, top-and-tailed by class 67 locomotives, required the leading engine to run-round in order to double-head the excursion away. These movements were an impossibility to undertake in the station itself with such a lengthy consist. Part of these manoeuvres meant propelling the train out of the yard and onto the down main line so it could draw forward into platform one. Departure was on-time at 05.00 which necessitated the re-platforming of the 05.02 F.G.W. service to Paddington onto platform two.
Although the excursion was heavily delayed en-route, arrival time at Edinburgh was only fifteen minutes late, and a more-or-less right time departure on return saw an arrival back at Worcester nearly twenty minutes EARLY. This caused a few problems at Shrub Hill as the excursion arrived before the late-running last train from Snow Hill. Luckily the train was top-and-tailed on arrival and after some deliberation it was decided to return the coaching stock to Crewe in this formation. The train ground to a halt on the Lickey incline and had to be assisted by a following freight service but eventually made it into Birmingham some time later.
Steve Widdowson's photograph shows a snow-encrusted 67030 being prepared to leave Worcester at one'o clock on the 2nd with the empty stock bound for Crewe.
Subscribe to:
Comments (Atom)